Write a project close-out report

Writes a close-out report for a non-software project covering objectives against results, budget and schedule variance, lessons learned and a handover of every open item to a named owner.

context

A close-out report lets the sponsor formally accept the project, release the team and budget, and know who now owns what is left. It is also the organisation's memory: the next similar project (an office move, an event, a building refurbishment, a process change, a marketing campaign) should start from its lessons. Close-out reports go wrong when they are a victory lap, when variance is hidden or computed wrongly, when lessons are generic ("communication could be better"), and when open items are listed with no receiving owner, so they quietly die once the team disbands.

Variance conventions to apply and show:

  • Schedule variance: actual end date minus planned end date, in days or weeks, and as a percentage of planned duration.
  • Budget variance: actual cost minus approved budget, in currency and as a percentage of the approved budget. State whether the budget figure is the original or the re-baselined one, and give both if both exist.
task

Write a project close-out report for .

project notes

Only if [ORIGINAL_GOALS] is given:

original goals

  1. If neither the notes nor the original goals say what the project set out to achieve, ask for the objectives and approved budget and dates, then stop.
  2. Compare each objective with the result: met, partly met or not met, with the evidence. If an objective can only be judged later (savings, satisfaction, adoption), mark it "to be measured", with when, how and who owns the measurement.
  3. Report scope: delivered as planned, added, removed or deferred, each with the reason and who approved the change if known.
  4. Compute schedule and budget variance using the conventions above. Show the arithmetic under Calculations. If figures are missing, use [need: …] and do not estimate.
  5. Write lessons learned that the next project can act on. Each lesson states what happened, the effect, and a specific recommendation ("Book the venue's technical walkthrough four weeks before the event; this year it was three days before and the projector wiring had to be redone"). Include what worked well, not only problems. No blame on individuals.
  6. List every open item (snags, warranty claims, outstanding invoices, documents, follow-up work, risks still live) with the receiving owner, due date and where the supporting information lives.
  7. Write a summary the sponsor can read alone: overall outcome in one sentence, headline variance, the most important lesson, and what you need from the sponsor (acceptance, a decision on an open item, closing the budget code).
constraints
  • Use only the supplied facts. Never invent figures, dates, approvals or feedback.
  • State bad news plainly: an overrun is an overrun, with its cause, not "a reallocation".
  • If the notes contradict each other (two different final costs), show both and ask which is right instead of picking one.
  • Body under about 900 words; detail goes in tables.
output format

Close-out report

  • Summary
  • Objectives and results: table with Objective · Target · Result · Status · Evidence.
  • Scope: table with Item · Change (delivered, added, removed, deferred) · Reason · Approved by.
  • Schedule and budget: table with Measure · Planned · Actual · Variance · Variance % · Comment.
  • Benefits to be measured: table with Benefit · Measure · When · Owner. Omit if none.
  • Lessons learned: grouped under What worked and What to change, each with a recommendation.
  • Open items and handover: table with Item · Receiving owner · Due · Where the information is.
  • Sign-off: what is requested from and a line for acceptance.

Calculations

The variance arithmetic, line by line.

Missing information

Bullets: each [need: …] and each contradiction to resolve. "None" if complete.

1 required value still a placeholder; the assistant will ask for it.

details

kind
Prompt: a task you run by name to get one finished thing back
domain
Writing and communication
category
Business writing
level
Intermediate
made for
Project / program manager, Operations, People manager, Consultant / freelancer
risk
read-only
version
v1.0.0 · incubating
reviewed
2026-10-03
works in
Claude Code, Codex, Cursor, GitHub Copilot, Gemini CLI, Antigravity, OpenCode, Windsurf, Zed, Continue, AGENTS.md, ChatGPT, claude.ai

Edit on GitHubReport a problem

use in

Hodios CLI
npx @hermes-hq/hodios install write-project-closeout-report --target claude-code
Agent Skills
npx skills add hermes-hq/hodios-dist --skill write-project-closeout-report -a claude-code
Add the Hodios marketplace (once)
claude plugin marketplace add hermes-hq/hodios-dist
Install the writing-communication plugin
claude plugin install hodios-writing-communication@hodios

The plugin brings every entry in this domain at once.

PromptBusiness writing

Write a project status report

Writes a project status report with an evidence-based RAG status, progress, risks, decisions needed and next steps, formatted as an email, a document or a single slide.

write-status-report
PromptBusiness writing

Write a handover document

Writes a handover for leave or a role change covering responsibilities, open work status, contacts, access, recurring tasks, known risks and first-week priorities, with gaps listed as questions.

write-handover-document
PromptMeetings

Plan a team retrospective

Plans a team retrospective with a format chosen for the team's situation, timed activities, facilitation prompts, ways to handle tricky dynamics and a follow-up for actions.

run-retrospective
PromptBusiness writing

Write an executive summary

Writes an executive summary of a long document that leads with the bottom line, the key points and the ask, using only facts from the source. Use before sending a report to busy readers.

write-executive-summary
PromptBusiness writing

Write an internal announcement

Writes an internal announcement of a reorg, policy change or launch that explains what is changing, why, the impact on each group and where to ask, plus an FAQ and a pre-send check.

write-internal-announcement
PromptBusiness writing

Write a project proposal or business case

Writes an internal project proposal or business case covering the problem, options, recommendation, cost, benefits and risks, and marks every missing number instead of inventing it.

write-project-proposal